Fri. 11-21-08 - They were installing the power, phone, cable, etc. when I stopped by at 1:00 pm. These are the guys that will be doing all the electrical work in the house, so we'll see a lot more of them later. The state inspection will be on Monday, and they'll backfill the ditch on Tuesday.
Friday, November 21, 2008
Wednesday, November 19, 2008
Power Lines Ditch 11-19-08
Wed. 11-19-08 - Drove up at 12:45 pm to check things out. They have dug the ditch to run the power from the new box to the house. Picture above I'm standing by the box facing the house. Picture below I'm in the garage facing the box.
Tuesday, November 18, 2008
Basement Slab 11-18-08
Wednesday, November 12, 2008
Backfilling - 3rd Day
Tuesday, November 11, 2008
Backfilling - 2nd Day
Tuesday, 11-11-08 - I'm standing at our "Front Door" taking above picture. In the picture below the top of the backhoe machine in the center of picture shows where the front door is.
Monday, November 10, 2008
Backfilling & Drainage Pipes Day
Thursday, November 6, 2008
Waterproofing Foundation